Distilling - energy
Steam distribution
Install a preventative maintenance and inspection programme
- employ written procedures
- inspect for changes / modifications since last inspection
Inspect for correct equipment to allow for:
Vibration expansion / contraction
Avoid condensate not draining from pipes
- pipe slope at least 1:240
- drain at least every 40 metres and at every low point
Control by valves
Steam trapping – Steam Traps
Insulate as much as possible
Including e.g. valves, flanges
Insulation thickness is optimised economically
- consider occasional reviews as / if fuel prices change
Cover hot liquid surface e.g. hot well
- lid, blanket, plastic balls
Target operating velocity for saturated steam is 30-40 m/s
- not higher else pipe damage can occur